Building Progress
Each year has two numbers: how many homes the city approved, and how many actually got finished. They’re different projects. A 2018 approval might finish in 2024 — or get cancelled, or change scope, or stay stuck. Read them as two separate paces, not a ratio.
—
Progress by Income Level
Cumulative new homes since the 2023–2031 cycle began, by required income category.
| Category | 8-Year Target | State Count (reported to HCD) |
Our Estimate (from city permits) |
% of 8-Year Target |
|---|
What “on pace” means: the cycle is 8 years (2023–2031). To finish on time, we’d need to be roughly year-elapsed ÷ 8 of the way there at any moment. So at the end of year 3 we should be at ~37.5%; at year 6 we should be at ~75%. The ✓ / ⚠ marks compare each row to that running benchmark.
What the income tiers mean (using the federal “area median income” or AMI — in SF for a family of 4 in 2024 that was about $174,500):
• Very Low Income — households earning under ~50% of AMI (under ~$87K).
• Low Income — 50–80% of AMI (~$87K–$140K).
• Moderate Income — 80–120% of AMI (~$140K–$209K).
• Market Rate — above 120% of AMI; what gets built without subsidy.
Every tracked housing project as a dot on the city — so you can see where the pipeline lives, block by block. Color = stage; pink = stalled. Try “Show stalled only” to see where approved homes are sitting, or filter to your district. Click any dot for the project’s address, size, and how long it’s been in its current stage.
Where Things Get Stuck
Construction itself takes a citywide median of 611 days (1.7 years). But getting from city approval to a building permit takes another 269 days — and earlier review stages add hundreds more. The bottleneck isn’t building. It’s everything before.
How Long Does It Take to Build?
Median time a housing project spends in each stage, from application to move-in.
Approved, Then Parked
Which Desk Has the File
“Longest stop” = the single review station where each permit spent the most calendar days. Review stations run partly in parallel, so station days don’t sum to total time. Hold time — often waiting on the applicant to respond — is broken out separately below, not blamed on the reviewing agency.
Station-by-station detail
| Review station | Dept. | Permits | Median days | Visits with a hold |
|---|
Planning vs. Its Own Clock
Share of reviews finishing over deadline, by year
Is Permitting Getting Faster?
Share of net-new-housing permit applications issued within 12 months of filing, by filing year. Only applications that have already had a full 12 months since filing are counted — for the most recent year that means early-year filings only, and the count shown in the hover reflects it. No projections. Medians for recent years would be misleading (only the fast permits have finished), so we count outcomes at a fixed horizon instead.
Biggest Stalled Projects
| Address | District | Homes | Current Stage | Days in Stage | |
|---|---|---|---|---|---|
| Loading project data… | |||||
District Scorecard
How is each district doing since California’s current housing goal began in 2023? Sorted by homes in pipeline. Click any row to see where projects are getting stuck.
How the scorecard is calculated (one deduplicated project per parcel; a project’s district comes from city permit records or its map location):
• In pipeline — homes in projects not yet completed (in planning, entitled, in permit review, permitted, or under construction) whose permit was filed since the state cycle began in 2023. Rows are sorted by this number.
• Completed since 2023 — homes in projects certified complete since the cycle began.
• Stalled now — homes in cycle-era projects currently tripping a stall test: entitled 2+ years with no permit application, permitted 18+ months with no construction start, or in permit review over a year.
• Median build* — median total days from first application to certified completion for the district’s projects completed since 2020 (a wider window than the counts above: the young 2023–2031 cycle hasn’t finished enough projects for stable per-district medians). The faster/slower tag compares this to the citywide median. Small districts’ medians swing on few projects — treat close differences as noise.