tldr;sf Housing Pipeline
San Francisco · 2023–2031 cycle

Are we building
enough homes?

California gave San Francisco 8 years to build 82,069 new homes. Three years in, we’re at about 5% of the target. The state-mandated mid-cycle review arrives January 2027.

Toward California’s 8-year goal

—

At this rate, by 2031

—

Approved but not built

—

—

homes short of California’s 2031 target if we hold our current pace.

Building Progress

Each year has two numbers: how many homes the city approved, and how many actually got finished. They’re different projects. A 2018 approval might finish in 2024 — or get cancelled, or change scope, or stay stuck. Read them as two separate paces, not a ratio.

View as

—

Progress by Income Level

Cumulative new homes since the 2023–2031 cycle began, by required income category.

Category 8-Year Target State Count
(reported to HCD)
Our Estimate
(from city permits)
% of 8-Year Target

What “on pace” means: the cycle is 8 years (2023–2031). To finish on time, we’d need to be roughly year-elapsed ÷ 8 of the way there at any moment. So at the end of year 3 we should be at ~37.5%; at year 6 we should be at ~75%. The ✓ / ⚠ marks compare each row to that running benchmark.

What the income tiers mean (using the federal “area median income” or AMI — in SF for a family of 4 in 2024 that was about $174,500):
• Very Low Income — households earning under ~50% of AMI (under ~$87K).
• Low Income — 50–80% of AMI (~$87K–$140K).
• Moderate Income — 80–120% of AMI (~$140K–$209K).
• Market Rate — above 120% of AMI; what gets built without subsidy.

About This Data

Where this data comes from

  • Building Permits — nightly via incremental publishing
  • Planning Dept Records — Projects & Non-Projects — daily
  • Development Pipeline — live, continuously updated (replaced quarterly snapshots in 2025)
  • Housing Production 2005–present — periodic, income-level breakdowns
  • MOHCD Affordable Housing Pipeline — quarterly, detailed AMI data
  • Dwelling Unit Completions — monthly
  • CA RHNA Progress Report — biweekly, official HCD numbers
  • Supervisor District Boundaries — static

How we track project timelines

Each project's timeline is reconstructed from permit filing, approval, issuance, and completion dates across city databases. Stage durations are calculated as the number of days between milestones. Median processing times are computed per stage to identify systemic delays rather than individual outliers.

How the review-attribution section works

  • Cohort: building permits filed since 2018 that propose more dwelling units than currently exist on the parcel (net-new housing). Alterations that keep the same unit count are excluded. Survivorship caveat: duration medians describe reviews that finished; open reviews are counted but can't contribute a duration yet.
  • Station data: DBI's Building Permit Addenda with Routing dataset — one row per review station per permit, updated nightly. “Days at a station” is calendar days from arrival to that station finishing. Stations run partly in parallel, so station days don’t sum to total permit time.
  • Holds: time a permit sits in hold status is reported separately and is not attributed to the reviewing agency — a hold frequently means the ball is in the applicant’s court.
  • Planning’s own clock: the Planning Department publishes its own review-time metrics with its own deadline targets. We report the department’s numbers against the department’s targets — not targets we invented. Rows Planning flags as potential data errors are excluded.
  • Official funnel: stage counts in “Approved, Then Parked” come from SF Planning’s own Development Pipeline dataset, using the city’s status classifications as-is.
  • Small samples: stations appear only with 100+ distinct permits; medians only, never averages; visits with negative or implausibly long recorded durations are excluded as data errors.

How we identify stalled projects

A project is flagged as "stalled" if it meets any of these conditions:

  • Entitled (approved by Planning) for 2+ years without a building permit application
  • Permitted for 18+ months without construction starting
  • In permit review for 1+ year without resolution

About the state housing target

California's Regional Housing Needs Allocation (RHNA) requires SF to plan for 82,069 new homes between 2023 and 2031, across four income categories. The state reviews SF's progress annually.

This dashboard shows two sets of numbers. The headline progress figure comes from the state's official records (reported annually by SF Planning to the CA Dept. of Housing and Community Development). We also show our own estimate derived from city permit data, which tends to run slightly higher because it includes some permit types the state may categorize differently. When the two numbers diverge, the state's official count is more conservative and is what SF is formally measured against.

What counts as “in pipeline”

Active pipeline = projects that have not yet received a Certificate of Final Completion or Temporary Certificate of Occupancy, AND whose permit status is still valid (not cancelled, withdrawn, expired, disapproved, revoked, suspended, or voided), AND that aren’t flagged as orphan records.

An orphan record is a project that’s nominally still “in pipeline” by status but has lapsed past realistic completion windows. We exclude three categories:

  • Entitlement lapsed — planning approval more than 5 years old with no permit ever filed. State law caps entitlement→permit at 3 years (extended 18 months by AB-2729), so a 5-year-old entitlement with no follow-on activity is functionally dead.
  • Permit review dead — permit filed more than 4 years ago with no approval ever issued. Permit review normally takes weeks-to-months; a 4-year-old open application is not a real ongoing review.
  • Ancient permit, no completion — permit issued before 2018 with no Certificate of Final Completion on record. The Dwelling Unit Completions dataset is sparse for older records, so these are almost certainly completed projects whose completion was never logged.

Excluding these prevents the active-pipeline count from being inflated by abandoned or data-orphan records. Today’s data flags roughly 32,000 such records out of ~57,000 total. The pipeline totals above also collapse multiple permits on the same parcel into a single project, so after both steps they count roughly 12,000 distinct projects (about 6,500 still in the pipeline, plus completions).

Known limitations

  • Income-category data is incomplete for market-rate projects. We assume non-affordable units count as market rate.
  • Some project records may not link perfectly across city databases. Our current match rate is shown in the data freshness section.
  • The live pipeline dataset updates continuously but depends on city staff data entry. Some records may lag real-world status.
  • This dashboard shows our best estimate from public data. Official RHNA progress is reported annually by the city to the state and may differ from these numbers. Where available, we show both.

Policy context

  • SF became subject to expanded streamlined approval (SB 423) in June 2024 after failing to meet its housing targets.
  • The city met its January 2026 rezoning deadline with the Family Zoning Plan, adding capacity for ~36,000 homes.
  • A critical trigger looms: if insufficient building permits are issued by January 2027, additional constraint reductions become mandatory under the Housing Element.